ready
Vision House · Rev 358 items · 48 trusted · 6 need decision · 4 deferred
Resolved
52 / 58
Takeoff
Vision House · Rev 3
Quantities with trust bands. Click any row for "why this number".
| Item | Qty | Unit | Source sheet | Plan · Schedule · Our count | Trust | Decision |
|---|---|---|---|---|---|---|
| Doors — D1 (single leaf) | 12 | nr | A-101, A-103, A-104 | 12 · 14 · 12 | Trusted | resolved → schedule 14 |
| Windows — W2 (1200×1500) | 8 | nr | A-101 | 8 · 8 · 8 | Trusted | autodetected |
| Concrete — slab (C30) | 74.6 | m³ | A-201, S-101 | 74.6 · — · 74.6 | Trusted | measured |
| Studs — 50×100 @ 600 c/c | 236 | m | A-201 | 236 · — · 236 | Trusted | measured |
| Outlets — double (medium) | 22 | nr | A-401, E-101 | 22 · — · 22 | Trusted | autodetected |
| Doors — D2 (double leaf) | 4 | nr | A-101, A-103 | 2 · 4 · 3 | Must-review | needs your decision ↓ |
| Brick — facing (single skin) | 62.4 | m² | A-301 | 62 · 70 · 62.4 | Must-review | needs your decision ↓ |
| Skylights — SK3 (Velux) | 3 | nr | A-501 | 3 · 3 · 3 | Verify | single source — please cross-check |
| Cabinets — base (kitchen) | 4.8 | m | A-601 | 4.8 · 4.6 · 4.8 | Verify | close but plan ≠ schedule |
| Steel beams — UB 305×165 | — | kg | S-201 | — · — · — | Unverifiable | needs your call |
| Floor finishes — tile (500×500) | — | m² | — | — · — · — | Deferred | skipped — re-cad later |